Scope & Challenges
Catalyst were tasked with carrying out Third-Party Commissioning Verification during the project.
Throughout the duration of the project, 34 inspections were carried out and over 250 issues were raised. These included:
- Discovering multiple discrepancies in the ventilation systems in over 30% of the units tested. The system was not achieving the required ventilation rates under Irish Building Regulation 2019 Technical Guidance Document F Ventilation.
- During inspections of the fire alarm system, it was discovered that the AOVs were not opening and closing correctly and, when the alarm was activated, the Fire Man lift in Block 3 was not dropping to the ground floor.
- All dry riser inlet breech valves were installed upside down.
Outcomes
Catalyst chaired an emergency meeting between the Client, Contractor, Subcontractor, and Specialist Contractor to discuss the discrepancies in the ventilation systems.
Re-Commissioned Ventilation System
Following this meeting, the ventilation system was re-commissioned, and Catalyst carried out sample checks to confirm that the ventilation system was meeting the requirements under TGD F.
Rectified fire Alarm System
The fire alarm system was re-demoed and the non-compliant issues were rectified.
Reinstalled Inlet Breech Valves
All dry riser inlet breech valves were reinstalled, the system was retested, and the installer supplied a new certificate.